Henry Clay Furnaces
| Name | Henry Clay Furnaces |
| Ortssitz | Reading (Pennsylvania) |
| Art des Unternehmens | Hochofenwerk |
| Anmerkungen | Eigentümer (1876/96): Eckert & Bro. Two anthrazite stacks, 1876: 45 x 12 bzw. 1896: 57 x 13; total annual capacity 1876: 13.000 net tons; closed tops. Betrieben mit Schuylkill Valley-Anthrazit. 1896: rebuilt several times; two Gordon-Whitwell fire-brick and three iron stoves; fuel, anthracite coal and coke; ores, hematite and magnetic from Berks and Lebanon counties; product, No. 2 foundry and gray forge pig iron ; total annual capacity, 36,000 gross tons. Brand: "Henry Clay". Selling agent, J. J. Mohr, Bullitt Building, Philadelphia. |
| Quellenangaben | [Ironworks of the United States (1876) 18] [Directory to the iron and steel works of the U.S. (1896) 12] |
| Zeit |
Ereignis |
| 1842 |
Bau des ersten Hochofens |
| Aug. 1844 |
Der erste Hochofen wird angeblasen. |
| 1855 |
Bau des zweiten Hochofens |
| Sept. 1856 |
Der zweite Hochofen wird angeblasen |
| Produkt |
ab |
Bem. |
bis |
Bem. |
Kommentar |
| Roheisen |
1876 |
[Ironworks of U.S. (1876)] |
1876 |
[Ironworks of U.S. (1876)] |
|
Zeit = 1: Zeitpunkt unbekannt
| Zeit |
Bezug |
Abfolge |
andere Firma |
Kommentar |
| 1876 |
Nebenwerk |
zuvor |
Eckert & Bro. |
Stand: 1876 |
|